Project: DaveBellairs   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).



Categories
  
Builder Name:Dave Bellairs   -  
Project:   Vans - RV-7   -   VIEW REPORTS
Total Hours:1467.9
Total Flight Time:
Start/Last Date:Jun 24, 2017 - No Finish Date
Engine:Lycoming IO-360
Propeller:Whirlwind 200RV
Panel:Advanced Flight Systems Avionics
 
Friendly URL: https://eaabuilderslog.org?s=DaveBellairs

Home or Last Project Picture

Dec 20, 2022     Empennage tip sanding - (2 hours)       Category: Tail Feathers
Sam applied some glass and epoxy to the right elevator tip transition seam. Sanded the previously applied glass and epoxy on both tips. Also sanded the right HS tip area where I filled a void from the factory.


 